Retrospective
Current story points completed:
- Diana Williams Oshun -> 25 Completed story points
- Christian Michael Lagura Yacapin -> 28 Completed story points
What went well:
- Finished all of the review tasks that were carried over
- Great insight with our supervisor meetings
- Better standing of hardware required
- Gained new perspective on our system
What went wrong:
- Assumptions on using a strong LLM model to carry all AI model task work was made too easily
- Functional Specification Markdown was not required (however is handy to have)
- Hardware
Start Doing:
No new notes were made
Stop Doing:
- Stop skimming stuff Christian
Continue Doing:
- Open communication discussions
- Flexibility on scheduled meetings
Facilitator: Christian Michael Lagura Yacapin
Attendees: Diana Williams Oshun, Christian Michael Lagura Yacapin